Time-line for the teacher housing project

Edgar's picture
March 10: Timber Lake School Board of Education approve purchase of two governor’s houses and other necessary expenses associated with the project (result in supplementing current budget approximately $120,000 in Capital Outlay).
March 10: Superintendent Larson/Wade Bollinger (Timber Lake Area Development President) attend Timber Lake City Council Meeting to finalize water line improvement.
Mid-March: Survey Lots 10 and 11 on Block 46
End of March/early April: Water line improvement
Early/mid April: Dig in sewer
Early/mid April: Dig in water
Mid/end April: Footings/frost wall
End April: Electrical
Early June: Houses moved in
June: Flooring/Appliances/AC/etc.
July 1: Houses available